Time | Item | Who | Notes |
---|
1 | General notes | Giorgio Cazzaniga | OTCC TST meeting held on 7/1. Here some notes on WT topics: - Face to face meeting: OTCC is planning different face to face meeting during 2019; we need as WT team to decide if there is any interest/opportunity to have a f2f meeting as well:
F2F Meetings for 2019 - March 18-22 Sydney - hosted by Cisco:
- Need to prep for the logistics information, in particular the invitation letter for visa application
- May 6-10, 2019 Beijing - hosted by FiberHome and China Mobile:
- Thanks to FiberHome & China Mobile for volunteering the site!
- September 2019 OIMT/OTCC meeting:
- Current plan is to meet at the ONF CONNECT meeting with rooms available to us for parallel working tracks
- December 9-13
- possible location is London, UK
- ONF Connect results: here the link to the material presented during ONF Connect event (December 2018): https://www.opennetworking.org/onf-connect-2018-collateral/
- WT addition to TAPI: we need to indicate as WT team if there is any interest to include WT specific parameters into TAPI
- Plan for WT activities:
1) alignment to Core 1.4 2) Backward compatibility: some discussions have been already done at TAPI level and there is an action point pending from Martin Skorupski and Nigel Davis to have a white paper/proposal to discuss; this discussion needs to be restarted in order to finalize a position
|
2 | PoC5 | all team | Remaining activities: - blog post: published by ONF and by Fierce Telecom:
and - detailed report/white paper: draft version available (under review by Telefonica)
- all contributions (essay) received
- ongoing Telefonica review for coherency and wording
- Missing: Executive Summary, Test Results and Conclusions
- It is requested to each Application providers to provide a short contribution for the test results and conclusions for their use case, as for example: all hw were connected to the controller and taken into consideration by the application, showing the expected results etc etc
- for the Conclusions we should take the blog post and use as conclusions (removing the duplicated parts)
|
3 | 2019 WT activities plan | all team | In 2019: - deliver TR-532 Rel1.1 formally
- Model: next version will be Rel.2.0:
- look at the open bugs in Mantis and decide the priority for the next release
- discuss about the alignment with the Core Model 1.4
- N.B. this model will not be backward compatible respect to 1.1
- 6th PoC: there is an interest from a Portugal operator to host this activity. Target will be also to involve higher number of operators.
|