Time | Item | Who | Notes |
---|
IM-D | Admin | Kam/Nigel | |
| | Kam/Nigel | - V1.4 deliverable spreadsheet (with document finishing time/date)
|
IM-E (more than two hours) | v1.4 | Nigel | - ControlConstruct model tidy up and update (Skip)
|
| | Nigel | - Photonic model update (See TAPI below)
|
| | Chris/Nigel | |
| | Nigel | |
| | Nigel | - Spec model enhancement for the photonic model (Skip)
|
| TAPI | Karthik | - Progress the Equipment model for TAPI (skip)
|
| | Nigel | - Photonic model
- OTSi Photonic Model discussion
- Higher priority than equipment
- Need the model before the draft
- Structure: link and NEP (not CEP),
- Issue to decide:
- Uni or bidirectional?
- C-band or L-band separate or together
- Level of deaggregation (separate WSS and transponder)
- Property is defined in ITU-T
- Mostly pass band
- NEP and CEP
- One layer: Layer Protocol Name = Photonic media
- Multiple Signal type: OTS, OMS, OTSiA
- Treat (manage) group of channels as a channel
- Contraint of formation of SMCG
- Can OTSiA be allocated to multiple SMCG?
- Action item - Stephane St-Laurent: to post the slide deck that was shared during the call
|
| Wireless transport | Martin | Nothing to discuss at this call |